7820 Dinmore Manor - The Blog

This blog will follow the heavy overhaul of 7820 through to its return to steam. The chassis is being overhauled at Tyseley Locomotive Works whilst the boiler is being overhauled at Ian Riley's workshops.
We are working hard every weekend to bring together the hundreds of small pieces that require refurbishing to get the loco back into working order. Follow us to keep up todate with the weekly progress and who knows if you like the look of what you see you may even be tempted to join us and help put 7820 back in action.

Monday, 11 November 2013

Saturday 9th November 2013 - Tyseley

 
The Final Frontier
 
 
The impressive sight of 7820's boiler standing on packing with Tyseley's steam crane in the background. This will now be used to lift the smoke box into place

 
Checking the packing under the firebox

 
The chimney arrives at Tyseley in readiness to be fitted to the smoke box. 7820 will carry the later elegant style of chimney fitted in the 1950's by B.R. after redrafting of the Manors

 
The cab roof receives some TLC. This cannot now be refitted until the boiler is in the frames

 
Some of the compensating links and a brake hanger pin have been machined by volunteers in readiness to complete the re-assembly of the brake gear.

2 comments:

  1. I take it by the comment about the BR 50's chimney that the livery will be BR green? or will it be something else?

    ReplyDelete