                              Through the last months of 2014, progress was being made on
                               re-bushing the brake gear for the new Dinmore Manor tender.

 
      The brake hanger brackets and top bushes in the brake hangers have
     all been renewed and the lower bushes that fit to the brake beams
 are also being renewed  

 
Some progress was made on the new plate work for the new drag box


                             The tender steps were removed to facilitate cleaning and painting
                             of the frames and the 'U' shaped angle iron that carries the various
                               engine to tender pipes was trial fitted to the new frame sections

 
    In late December, the frames moved to Toddington for completion of
  the drag box and will remain there for re- erection. After removal of
     the frames, the new 3,500 gallon tank which replaces the original 4,000
 gallon Collett tender tank was placed on the jacks
 
 
    New rubbing blocks for the brake hangers have been cast and
 are being machined in readiness for fitting
 


                                 The brake shaft is currently 'off-site' for machining work to be
                                 completed on it and the links from this shaft to the adjusting
                                                   screws have been re-bushed