We are working hard every weekend to bring together the hundreds of small pieces that require refurbishing to get the loco back into working order. Follow us to keep up todate with the weekly progress and who knows if you like the look of what you see you may even be tempted to join us and help put 7820 back in action.

Monday 21 January 2013

Refitting the weighbar shaft.

The following set of photos show the installation of the weighbar shaft into the frames and represent the start of the installation of all the valve motion.
First job to make sure the bushes are spot on and the grease will be distributed along the shaft where it is required.

With the bearings on the ends of the shaft everything is suspended from the gantry and lowered into the holes in the frames.
One end is slid right through the frame hole to allow the opposing end to drop down inside the frames.

The entire aseembly is then slid back to centarlise it in the frames.

Lastly a bit of final adjustment to get the fitted bolts into the frames and the locking rings secured on the shaft.